Progress & Action PlansLatest newsThe project report is now complete. Follow this link to download it. Project presentations are also complete. Long-term Project Plan
[Back to top] Project Planning
Started: 25 February 2003
[Back to top] Stage One - Working application with limited featuresThe first stage delivers a simple application that implements some functionality at each of the data, processing, and presentation layers. The analysis and design will be most important as this stage lays the foundation for stages 2 & 3, which add functionality.
Estimated Start: Mid-semester Break
[Back to top] Stage Two - Refactor and Add FeaturesRe-iterate through software development cycle, adding the most important features.
Estimated Start: Inter-semester Break
[Back to top] Stage Three - Continue to Add FeaturesRe-iterate through software development cycle, adding other new features (as time permits).
Estimated Start: First quarter of Semester 2
[Back to top] Project Completion
Estimated Start: Mid-semester Break
|
Final Project Presentations
10:00am Thursday 23 October in meeting room 731.324.
Demo Screenshots
Updated screenshots of the demo demonstation application are now available. View Screenshots (Word document)
Mid-year Project Presentation
10:00am Thursday 5th June in meeting room 731.324. View Powerpoint Presentation View Summary Document Download mid-year report (Word document) |