         9/04/2004

Planning for VPSS Complete

         17/04/2004

1st Class presentation

17/04/2004

Project schedule due

24/04/2004

Analysis of VPSS Complete

15/05/2004

2nd Class presentation

15/05/2004

Project specification due

25/05/2004

Design of VPSS Complete

09/07/2004

Coding of VPSS Complete

02/07/2004

Mid year report due

25/09/2004

3rd Class presentation

08/10/2004

Project Handover (incl. Final report and documentation due)

15/10/2004

Project exhibition

 