Project initiation Started: 22/03/2006 Ended: 3/04/2006

Included: Introduction to he natrue of the project, demonstration current application, arranging the resources(Laptops and software will be using) and introduction to the staff members in the company

Preparing documents Started: 1/04/2006 Ended: 8/04/2006

Included: The project brief, project schedule, presentation slides.

1st presentation 8/04/2006 8/04/2006

Included: Deliveried the presentation on 7/042006 Morning to the class and supervisors and staff members from the company

Functioanl requirement gathering for the frame work 16/04/2006 26/04/2006

Included: Interview user of the current version of "Processwizard" and understand the set of requirements set by the sponsor refining the functionalities

Module overview Introduction and demonstration/exerciese 1/05/2006 3/05/2006

Included: brief introduction to the module's funcationalites and the components it contains. Did a sample exercise about this module manually.

Second documentation preparation 8/05/2006 8/05/2006

Included: Creating Entity-relationship-diagram.

Finding the interface tool candidates and testing thier usability 25/06/2006 30/06/2006

Included: Trying finding the candiates on the internet and testing these candidates

Developing an application and write up a purchasing purposal 1/7/2006 10/07/2006

Included:Based on the selected interface tool develop an application, using the perpared a tool purchaing purposal

Developing the second application using the interface tool and the diagramming tool 11/07/2006 18/07/2006

Included: using the selected diagramming tool and interface tool developed a 3tier application