Summarised Achieved Goals
|
Summarised Unachieved Goals
|
|
Preliminary RESCare Code Review |
Completing the coding of the software |
|
Functional Design Specification Revision |
|
|
Technical Design Specification Revision |
|
|
Test Plan and Case Revision |
|
Issues & Risks
1.Team Member Unavailability
Two of the 340 team has been ill during the implementation phase,
which has bee detrimental on our project progress. One of hte team
members was away from the project for two whole days whilst the other
kept working at the company. Two of our team members are taking four
papers this semester, which is will limit the time spent working on
the project.
2. Modified Design
As mentioned before, the design of the Care Plan prototype has
been substantially modified. The redesigning of the prototype
took time and the consequence of the redesign was the revision
of the existing documents that were already finalized for the
previous design.
Monthly Report for August.doc