Activities On Auguest

Summarised Achieved Goals

Summarised Unachieved Goals

Preliminary RESCare Code Review Completing the coding of the software
Functional Design Specification Revision
Technical Design Specification Revision
Test Plan and Case Revision

Issues & Risks

1.Team Member Unavailability

Two of the 340 team has been ill during the implementation phase, which has bee detrimental on our project progress. One of hte team members was away from the project for two whole days whilst the other kept working at the company. Two of our team members are taking four papers this semester, which is will limit the time spent working on the project.

2. Modified Design

As mentioned before, the design of the Care Plan prototype has been substantially modified. The redesigning of the prototype took time and the consequence of the redesign was the revision of the existing documents that were already finalized for the previous design.

Monthly Report for August.doc