Infrastructure Progress
Period Objectives Status
March Project briefing
Training
Start up planning
Allocation of responsibilities
Completed
April Market Research
Business Modelling
Completed
May Stream Plan Finalising Completed
June Stream Milestone 1 Completed
July Stream Milestone 2 Completed
August Stream Milestone 3 Completed
September Stream Integration Pending
October Project Review and Final Reporting Not Started

Hostel Progress
Period Objectives Status
March Project briefing
Allocation of responsibilities
Completed
April System Design
Budgetary Costing
Completed
May Detailed Design
Contract Proposal Invitation
Completed
June Award of supply and installation contracts Pending
July Preparation of operation manuals Revised
August Supervsion of contractor progress Revised
September Supervision of Installation Revised
October Commissioning and Operator Training Revised