Period
|
Objectives
|
Status
|
|
March
|
Project
briefing, Allocation of responsibilities
|
Completed
|
|
April
|
Market
Research, System Design
|
Completed
|
|
May
|
Issue
RFP, Budgetary Costing
|
Completed
|
|
June
|
Finalise
User Requirements, Issue Tenders
|
Completed
|
|
July
|
Award
Supply and Installation Contracts
|
Pending
|
|
August
|
Preparation of Operation Manuals
|
Delayed
|
|
September
|
Supervision of Contractor Progress
|
Delayed
|
|
October
-
December
|
Supervision of Installation, Commissioning
and Operator Training
|
Delayed
|