0100,0100,0100Afternoon All,
The work breakdown structure is a method of structuring work
scope. It is the first activity that is undertaken when dealing with
projects and breaks the project into manageable sections.
For this assignment you are required to examine the whole project
and provide a WBS to three levels for the whole project and
selecting one area only provide a 4th level.
The way you break the project down is up to you and it must make
sense.
Attached are the notes on WBS and they are repoduced here
I can not get onto eeserver so this information is also in the U drive
of the NT's under EPM444
leftHIERARCHICAL METHODS
leftThese methods attempt to successively
refine the definition of scope. They are
the most common method of scope
organisation.
leftThese methods are useful in providing
scope checklists and allow for detail to
grow with the project.
leftOther requirements for these systems
include:
outManageable where specific authority and
responsibility can be assigned
outIndependent or with minimal interfacing
with other elements
outcan be integrated to give an overall
picture
outMeasurable in terms of progress.
leftThey however can create divisions in
organisations as to the split of work
responsibilities. Care should be used in
designing these systems to ensure
interface points are defined and agreed.
leftThese structures can also grow in size
at a rapid rate leading the generation of
"clerical monsters".
leftTYPICAL STRUCTURES
leftStructures vary from one organisation to
another and one project to another. A
hierarchical structure may comprise:
Level
Description
1
Total Program
2
Project
3
Task
4
Subtask
5
Work Package
6
Level of Effort
leftThe upper three levels are usually
specified by the client. Level 1 is
usually used for authorisation and
release of all work, budgets are
prepared at level 2, schedules at level 3.
leftThe top 3 levels represent integrated
efforts and should not be applied to a
department.
leftThe summation of all elements in one
level must be the sum of all work on the
next lowest level. Each element of work
should only be assigned to one and only
one level of effort.
leftIn setting up a system, the following
should be considered:
outThe technical and complexity
requirements of the program
outThe program cost.
outThe time span of the program.
outThe executor's resource requirements.
outCustomer and contractor internal
management control and reporting
structures.
outNumber of organisations involved in the
project.
Chris Croft email: ccroft@ee.uwa.edu.au
phone: +61 8 9380 3097 fax: +61 8 9380 1065
Dept. of Electrical & Electronic Engineering
The University of Western Australia
NEDLANDS WA 6907 Western Australia