Mark's Btech450 webpage

Welcome to my Btech450 / IS340 project web page. Here you be able to find out about all the major happenings and events regarding my project with Optimation NZ as they happen.

Milestones

13 October 2005

Setup Project Exhibition at the University of Auckland Conference Center.

2 October 2005

Delivered final handover presentation onsite at Optimation.

30 September 2005

Delievered final technical documentation and manuals to the University.

26 September 2005

Delievered final class presentation at the university on the 24th of this month.

20 September 2005

Generating a report feature set complete

12 September 2005

User Interface design / look and feel begins

10 September 2005

Updating a customer's details feature set complete

08 September 2005

Monitoring a survey feature set complete

06 September 2005

Distributing a survey feature set complete

01 September 2005

Filling in a survey feature set complete

30 August 2005

Authenticating a customer feature set complete

26 August 2005

Creating a survey feature set complete

18 August 2005

System Architecture documentation complete

09 August 2005

Maintaining a survey question feature set complete
Maintaining a survey template feature set complete

02 August 2005

Authenticating an Internal User feature set complete.
Maintaining an Internal User feature set complete
Maintaining a contact / distribution list complete

18 July 2005

This past week we have confirmed that the front-end of the system will be developed using Laszlo, meaning some slight changes in the front-end architecture of the system. The Laszlo-based front-end will now be communicating with our .NET WebServices at the Server-side, using SOAP. Our Server-side however can remain unchanged due to our n-tier based architecture.

27 June 2005

Project activities resume - Finalising design documents and beginning development.

4 June 2005

Project activities put on hold due to examination commitments.

30 May 2005

FDD Features List finalised.

7 May 2005

Delivered Project Specifications presentation at the Old Choral Hall lecture theatre and handed in the Project Specifications document.

28 April 2005

Completed Requirements document.

18 April 2005

Completed Vision and Scope document for the Customer Survey Engine project.

9 April 2005

Delivered project schedule presentation at the Old Choral Hall lecture theatre.