Task Completed
|
Onging Task
|
|
Function Design Specification Documentation Complete |
Learning Delphi 5.0 |
|
Technical Design Specification Documentation Complete |
Start coding the Functions for Care Plan Module |
|
Test Plan Documentation Complete |
Review Interface Design of Care Plan module |
|
Care Plan Interface Design Complete |
|
|
Test Case Specification Documentation Complete |
|
Issues For July
1.Workstation
Although it was one week late, the workstation that MedTech had promised the
340 team would have for implementation arrived. One of the team member went and assembled
the machine and installed all the necessary software for implmentation as soon as the
340 team was allowed to do so. The following the day, it was discovered that another
employee had took the machine and reinstalled the software on the machine and
used it for his purposes. Thusthe 340 team had to assemble anohter one and reinstall
the software again. A week later, it was discovered that MedTech was short on one new machine
and the macine allocated to the MedTech 340 team was replaced with an older machine.
Furthermore, there will be only one machine that is available for the 340 team to use
in the company for implementation and implementation related activities, which could
hinder the progerss of the project. Further to this, working on the code outside the compant
is almost impossible as the 340 team is not permitted to take the existing code
outsdee the premises of MedTech........
2. MedTech Project Supervisor Unavailableilty & Replacement
At the end of the month, the 340 team MedTech project Supervisor Sulav Giri,
will be away on holiday for two weeks. This could be an issue, as he knows about the
project best in MedTech. Sulav will be appointing another Project Supervisor in MedTech
oversee the requirements of the 340 team..........
Risk
Delphi is new development language to the 340 team. The risk is that
the 340 team may not have the competence in developing all the functionalities
in the proposed software as some of the design is qite complex. Therefore it is
a risk in that the 340 team may not be able to develop teh solution that they have
proposed which may have to be scaled down and may not meet the requirements ofhte software.
Monthly Report for July