Timeline for Milestones

Project Completed!

March
31 - First Initial Meeting with sponsor
April
17 - Project Schedule Document and Presentation
 
May
15 - Project Specification and Presentation

23 - Complete CMS Research and Start CMS Trial and Test

31 - Compete ASP.NET Training

 
June
07 - Finish evaluating Macromedia Contribute2

29 - Finish evaluating WebDirector

July

05 - Finish evaluating Straker ShadowMX

15 - CMS Trial and Test phase completed

18 - Starting Farmers website migration to .NET platform

29 - CMS presentation to the sponsor

August

27 - Finish the development phase

31 - Start on System and User Documentation as well as the Training

September

25 - Technical documentation and presentation

27 - Project Handover to sponsor

October

01 - Go Live!!
15 - Project Exhibition

 

 

Most Recent:
  1. Project Exhibition
  2. Final dinner party at Langston

horizontal rule

Home | People Involved | Schedule | Archive | Contact Information

 Copyright or other proprietary statement goes here.
For problems or questions regarding this web please contact us.
Last updated:
11/11/2004