HOME PROJECT PROGRESS
TEAM EVENTS

-PROGRESS-
March | April | May | June | July | August | September

MARCH
14 March - Formed a team with Karl and Gary
19 March - Made our business proposals
22 March - Sponsor project was allocated, we got the Navy Project
25 March - Had our first meeting with the Navy

Back to Top

APRIL
1 April - Had a brief meeting with the Navy
10 - 15 April - worked on our project brief and project schedule
16 April - Presented the Navy our Project Brief and Presentation
17 April - Project Brief Presentation: The big day, we presented our Presentation after morning tea
23 April - We had our monthly meeting with our project supervisor - Lech Janczewski and discussed over our plans for the next month and the specification documentation.
27 April - We had a meeting with the Navy to discuss about the systems specifications

Back to Top

MAY
3 May - Our first monthly report (April) was due in today
6 May - We had a meeting with our project supervisor Lech about our April report. Discussed about the contents in the report and our plans for the upcoming month.
8 - 13 May - We went hard on our specification document through these days and did our own individual research on the different components/technical parts that related to our system.
14 May - We had a meeting with our project sponsor and went through the specification presentation.
15 May - Our big day for our second presentation, specification presentation. We were in the morning session, Peter Buell was really kind to come along for the day to help us with our presentation.
28 May - We found out that our project supervisor peter buell got changed to a different position. So our new project supervisor from the Navy is Matt Williams who will be helping us through the rest of the project.

Back to Top

JUNE
1 June - Handed in our May monthly report.
3 June - We attended the Harbour Side safety check at the Navy. Unfortunately when we got to the ship the evaluations had already finished but we were lucky enough to be shown around the ship by Lieutenant Commander Matt Williams. It truly was a great experience. Check out the photos link.
9 June - We all attended the Sea Side safety check for the Te Kaha. We got to stay overnight in the ship, lucky for me I only have to share a cabin with another Lieutenant. While karl and Gary had to stay in a room with 10 others. During our stay we had a real life visual of the exercises that were conducted for the sea side safety check. This helped our understanding of the MOETs operations alot more and clarify some of the uncertainties.
10 June - We got back to the Navy base in Devonport at around 7.30am. We had a very brief debriefing with Matt about the trip and our plans for June. We then had a our monthly meeting with Lech and discussed our plans for June and exams.
16 June - Me and Karl went to pick up our laptops from the Navy. We're all quite excited about it. Finally we could start our implementation process.
5 - 25 June - Exam break, We all took time off to concentrate and study for our own exams.

Back to Top

JULY
2 July - We attended the Complusory Dynamic Workshop held at the Kelston Community Hall in Henderson.
8 July - We've finally started our systems implementation.
15 July - We had a meeting with our supervisor, Lech at the Navy base and discussed the possibility of getting a physical PDA to do development.
30 July - I went to the Navy and picked up the PDA that the Navy is going to be using for our system

Back to Top

AUGUST
12 August - We had a meeting with our supervisor, Lech and discussed our plans for the following month.
16 August - Submitted our monthly confidential survey.
23 August - Me and Karl went to the Navy to have a meeting with our project supervisor, Kelvin. We discussed some of the specifications for the project and some hardware issues. We also found out that most of the MOET team will be away for two weeks including our project supervisor.

Back to Top

SEPTEMBER
1 - 24 September - We are all coding and implementing the three different sub-systems.
25 September - We presented our final presentation to the class in the afternoon.
26 - 30 September - We've finished all our systems implementation. Now we're working on our technical documentations and user manuals. Which we need to hand in 2 days before our project handover.

Back to Top

Photos

E-mail











:. Created by JiNnY .: