Current Status
*More detailed reports are available in
the Progress Reports menu - it shows the progress of the project on a monthly
basis.
-
Graduation dinner with INFOSYS 340 students
23/10/03
-
Official Handover 16/10/03
-
Preparation for final presentation and handover
10/10/03 - 15/10/03
-
Perform intensive testing for all modules
2/10/03 - 10/10/03
-
Begin documentation for system 1/10/03
-
Class presentation conducted 27/9/03
-
Prepare class presentation 24/9/03
-
Show company sponsor beta-version of our Asset
Management System 14/9/03
-
Finished coding for "PC module". Begin coding
for last module of the system - Check-In/Check-Out 10/9/03
-
Started the "PC and ""Books" module.
19/8/03
-
Finish our "Software" module. 18/8/03
-
Started on the "Software" asset module and finishing
off the "Hardware" module 7/8/03
-
Lech came to ACE and test out the system that we have
develop so far. 28/7/03
-
Still working on "Hardware" asset.
21/7/03
-
Started coding. Working on "Hardware" asset.
10/7/03
-
Finish developing database. 8/7/03
-
Right now we are in the stage of developing the
database. 2/7/03
|